Some of the floors are in. The tiles have been glued down in the plant room. The floor isn’t dry or grouted yet, but the tiles are down. Take a look.
Here is the other side of the room.
Gorgeous floor! You gotta love that floor!
Meanwhile, the oak floors have been delivered. There is a pile of oak in the den.
There is more oak upstairs in one of the bedrooms.
That is a lot of boards! (I have heard that somewhere before)
Some of the doors are in too.
The door on the left goes from the mud room down into the garage. The door on the right goes from the mud room up into the garage attic. Sooooo, since we are standing in the mud room (figured that out, did ya?) if we turn around and look the other way…. we see….
The lower cabinets have been installed in the laundry room. The upper cabinets are still in their boxes. These cabinets are just plain white, with doors made of MDF (Medium Density Fiberboard) and particle board cases, but they are certainly fine enough for the laundry. And they are about 10,000 times better than the cabinets we had in the kitchen of that other house.
Some of the tiles have been installed in here as well.
Looks nice.